Construction of a 1,000 MW combined-cycle power plant is progressing rapidly in the Turkistan Region
22
17 November 2026
This large-scale infrastructure project is designed to address the energy deficit and ensure a reliable electricity supply to the southern regions of the country.
A total of 2,455 specialists are currently working at the site (2,281 during the day and 174 at night), supported by 184 pieces of equipment. Particular attention is being paid to ensuring safe working conditions.

The following key milestones have been achieved to date:
* Overall project progress: 81.7%;
* External power supply networks (112 km): 95.4% complete;
* External gas supply network (13.6 km): 99.9% complete;
* Water supply system: 97.5% complete;
* Access road (3.1 km): commissioned;
* Construction and installation works at the main site: 60.1% complete;
* Cable networks: 537.1 km laid, representing 41.1% of the total scope;
* Water supply and sewerage networks: 12.3 km of the planned 30.8 km laid (40%);
* Gas pipeline network: 1.65 km of the planned 1.66 km laid (99.4%).
The project is being closely monitored by the Fund. Once completed, it will help ensure a reliable and uninterrupted electricity supply to the country’s southern region and strengthen Kazakhstan’s energy security.

{{ $t('messages.news1') }}
STATEMENT BY THE PRESS SERVICE OF SAMRUK-KAZYNA JSC
{{ $t('messages.news1') }}
Nurlan Zhakupov Calls for Investment Projects to Be Delivered on Sched...
{{ $t('messages.news1') }}
Prime Minister Olzhas Bektenov Chairs Meeting of Samruk-Kazyna Board o...
{{ $t('messages.news1') }}
AZCON Holding Draws on Samruk-Kazyna’s Experience in Managing Large-Sc...